EXECUTIVE ORDER 13274
Task Force Agency Representatives Meeting Minutes
726 Jackson Place
Lincoln Conference Room
2:30 p.m. - 3:30 p.m.
November 17, 2004
Call to Order: 2:04 pm
Chair: Mary Peters, Administrator, Federal Highway Administration
I. Introduction and Opening Remarks
FHWA Administrator Mary Peters called the meeting to order at 2:04 pm. She
thanked the Council on Environmental Quality for hosting the meeting and made
a few opening remarks. She said that FHWA had just released its annual report
to Congress on its environmental streamlining activities for 2003.
Administrator
Peters noted that FHWA and FTA are operating under the fifth short-term extension
of TEA-21 and said that Congress is unlikely to pass a
reauthorization bill until the 109th Congress. She also called attention
to a handout regarding FHWA’s continuing commitment to wetlands protection.
II. Status of Priority Projects
Stillwater Bridge / St. Croix River Crossing
Michael O'Malley, DOT project
champion for the Stillwater Bridge project, provided some background on the
project, noting that the proposed bridge crosses
a designated Wild and Scenic River. He noted that in October the stakeholder
group reached a tentative agreement to build a bridge along one of the alignments
identified in the Draft EIS but with an improved bridge design. The agreement
includes maintaining the existing historic lift bridge and incorporating
it into a pedestrian/bicycle trail between the two states. This preliminary
agreement
is contingent on the development of an acceptable mitigation package. The
Final EIS is expected in January or February 2005.
He thanked the National Park
Service for helping the stakeholder group work through the requirements of
the Wild and Scenic Rivers Act. Laura Deans of
the Advisory Council on Historic Preservation noted that a critical feature
of the tentative agreement is that the Minnesota DOT will maintain ownership
of the lift bridge, which addresses concerns about liability and the cost
of maintaining the bridge. Upon questioning, Mr. O'Malley added that the new
bridge
design will add $45 million to the cost of the bridge.
Paul Hoffman of the
Department of Interior said that the stakeholder group process was very helpful
and this project is an example of what a good stakeholder
process can accomplish. It gave everyone an opportunity to engage and participated
in the process. He noted that using a stakeholder process takes time but
can be quicker in the long run since it can prevent lawsuits that can stop
a project
dead in its tracks. He said that when some people hear the word “streamlining” they
assume that it means that some environmental protections will be weakened,
but this project is a good example of how the process can address all needs
and result in a better outcome.
Ms. Deans added that the stakeholder process
also fulfills the requirements of Section 106 of the National Historic
Preservation Act. She said that she
is working with Cheryl Martin of FHWA’s Minnesota Division to develop
some lessons learned to share with other project champions.
Administrator
Peters said that the result of the stakeholder process is consistent with
what President Bush envisioned when he signed the executive order. She
thanked all of the participants for their hard work and perseverance on this
project.
Lower Manhattan Transportation Recovery Projects
FTA Administrator Jennifer
Dorn gave an update on the status on the three Lower Manhattan priority projects.
She said that the Final EIS for the Fulton
Street Transit Center was issued last month and that a Record of Decision
(ROD) is expected soon. The Final EIS for the PATH station will likely be issued
in January 2005. A Finding of No Significant Impact (FONSI) was signed for
the South Ferry Subway Terminal in August 2004.
Administrator Dorn said that
FTA is interested in capturing the lessons learned from these three projects.
Because the projects were in response to the attacks
of September 11, the characteristics of the projects are unique. However,
there are also lessons that can be applicable to other projects.
For the Fulton
Street project, the period from Notice of Intent to ROD was 20 months when
a period of four years is more typical. Some unique attributes
of the project contributed to the speed of the process. For example, the
federal government paid 100 percent of the costs, so there were no local financing
issues. Also, the projects were centered in one community, so the agency
did
not have to engage as many communities as is typical for a linear transit
project.
Administrator Dorn also attributed the speed of the process to several
factors that could be lessons for other projects. First, there was a memorandum
of
understanding (MOU) that helped consolidate the period for decision-making.
For example, the MOU established a ten-day review period. Second, upfront
work, particularly by EPA, allowed participating agencies to agree a framework
for
environmental analysis before things got started. This agreement sped up
the work and improved its quality and consistency. Third, environmental performance
commitments were incorporated into the project. MTA and the NY/NJ Port Authority
agreed to measures to reduce noise and air pollution. These agreements will
be incorporated into the FONSI and ROD. FTA also worked closely with victims’ families
to establish a joint process to discuss and address historic preservation
issues. The agency worked with ACHP and used a mediator.
Administrator Dorn
expressed interest in having outsiders talk with the project
team to figure out which lessons learned are applicable to other projects.
Administrator Peters expressed support for the idea and suggested a facilitated
discussion. She also noted again that without the willingness to work together,
the participating agencies would not have made such significant progress
on these projects.
III. Report to the President
Bryan Hannegan of CEQ said that there is no substantive problem with the Report
to the President, but CEQ has not had a chance to sign-off on the document.
He pledged to keep working with his colleagues to get his agency’s sign-off
as soon as possible.
IV. Other Environmental Streamlining Efforts
Fred Skaer, Director of FHWA’s Office of Project Development and Environmental
Review, laid out four topics for discussion:
- The 50th anniversary of the National
Highway System,
- Policy paper on Section 4(f),
- FTA/FHWA legal memorandum on linking transportation
planning and NEPA, and
- Guidance on NEPA and toll-financed highway projects.
50th Anniversary of the
National Highway System
The National Highway System is turning 50 years old.
Every year, additional sections of the highway system are turning 50 and
becoming eligible for designation
as historic property. This development has the potential to complicate the
maintenance and improvement of the system. Mr. Skaer said that FHWA had been
was working on a legislative fix and an administrative fix at the same time.
Now that TEA-21 reauthorization had been postponed again, the agency is now
betting on an administrative fix. It is seeking an administrative exemption
from National Historic Preservation Act.
Mr. Skaer said that ACHP is meeting
today and that a committee on federal programs is taking up the proposed
administrative exemption. He said he hoped
that ACHP will approve the exemption and that it can be published in the
Federal Register. He said he hopes to have something finalized by the end of
the calendar
year.
Policy paper on Section 4(f)
FHWA is updating its policy on Section 4(f). The
paper has been sent to the Departments of Interior and Agriculture (USFS)
and to ACHP for comments. Mr.
Skaer said that he anticipates some wrinkles to iron out, but he expects
no major issues at this point.
FTA/FHWA Legal Memorandum on Linking Transportation
Planning and NEPA
FHWA Chief Counsel D.J. Gribbin asked Task Force Members
to submit comments on the joint FTA/FHWA legal memorandum about linking transportation
planning
and NEPA. The two agencies would like to get the memo out by the end of the
month. Dinah Bear of CEQ said that the memo was fundamentally sound but that
CEQ has submitted some comments.
Regarding the draft questions about linking
planning and NEPA that were previously distributed, Mr. Skaer said a question-and-answer
format will be helpful to
field staff. He said that some comments have come back, and he welcomed further
comments. The intent is for the questions and answers to be distributed as
guidance, and the legal memorandum be maintained as the background justification.
FTA and FHWA will be drafting answers to the questions over the next month.
The agencies have done some outreach to Metropolitan Planning Organizations,
State DOTs, and non-governmental organizations. He stressed that the actions
addressed in the memo are optional, not a requirement.
Administrator Peters
noted that this guidance is being developed in response to several states
that want to better link transportation planning and NEPA.
Mr. Skaer said that some of the existing guidance is problematic, so new
guidance is warranted. Mr. Skaer asked for comments on the questions themselves
within
a week. The answers to the questions will be distributed later for comment.
Memorandum
on Toll Roads
FHWA has been working with Colorado DOT regarding the NEPA review
process for toll-financed roads. The main question is whether NEPA requires
analysis
of a non-toll alternative. Colorado DOT is concerned that NEPA requires them
to look at both toll and non-toll alternatives even when they have a toll
project in their fiscally constrained plan. The State DOT does not want to
spend time
and resources on studying non-toll options when they cannot afford to go
that route. The state also does not want to mislead the community by analyzing
non-toll
options when they are not really an option.
Ann Miller of EPA asked why the
funding source should affect the choice of alternatives for review under
NEPA, since alternatives generally focus on different
modes or locations. April Marchese of FHWA said that in general the funding
source should not affect the choice of alternatives, but in some cases it
does. She said choice of toll financing should not limit the analysis of different
corridors.
Administrator Peters asked whether the choice of toll financing
would limit the choice of capacity of the project or other aspects of the
project’s
location or design. Ms. Marchese said that the memo wasn’t focused
on that aspect of the problem.
Mr. Gribbin observed that in the future toll-financing
of roads will be more
common, so it is important to provide more guidance on how environmental
reviews should be done for them.
V. Working Groups: Discussion of Next Steps
Purpose and Need Work Group
Pat Haman of EPA (standing in for Pam Stephenson
of FHWA) provided a summary of the recent activities of the Purpose and Need
Work Group. The Work Group
has met twice since the contractor, ICF Consulting, submitted the Sept. 30
draft report. The report highlighted several important issues. It identified
the need for guidance on the appropriate length and format of purpose and
need statements. The report identified a need to clarify the appropriate use
of
economic development as a purpose and need for transportation projects. The
draft report also suggests that additional guidance might be needed on the
role of cooperating agencies and what constitutes “substantial deference” to
the lead agency. She said that the Work Group’s thinking is that the
guidance should be directed at practical issues and that legal clarification
is not needed.
While the draft report contained useful information, the Work
Group decided it needed to ask the contractor for more details in a couple
of areas. For
example, the Work Group would like more information on NEPA/Section 404 merger
agreements and their dispute elevation procedures. Also, the Work Group would
like more information on how resource needs are affecting early participation
by resource agencies. The Work Group is waiting for a revised report from
the contractor to address these questions.
Ms. Haman said that upon receiving
the revised report, the Work Group would like to proceed with developing
guidance documents addressing the need for
concise statements, as well as the proper way to address economic development
as a primary or secondary purpose. In the interim, the Work Group would like
the Task Force to approve the posting of the list of laws and regulations,
guidance documents, and training opportunities relevant to purpose and need.
The Work Group does not think that the draft report is ready for public release.
It would like some feedback on whether the three Work Groups can post different
materials to the public website.
Mr. Skaer reminded the Task Force that at
the previous meeting the Work Groups were designated as the gate-keepers
for deciding which materials to release
to the public. Dinah Bear of CEQ raised an issue of whether it would raise
questions if the other two Work Groups are planning to post draft reports
to the web but the Purpose and Need Work Group does not post its report at
this
time. Administrator Peters initially expressed a preference to wait until
reports are final to make them available to the public.
Ted Boling of CEQ, however,
said that the Indirect and Cumulative Work Group would like to post its report
to the web as a draft to get public input. He
recommended that Task Force Members have thirty days to review the Work Group
baseline reports before they are posted on the public website. This is also
the recommendation of the Integrated Planning Work Group. Administrator Peters
proposed that web posting of the draft reports take place after the full
Task Force has had a chance to review them, and recommended consistency in
terms
of vernacular in describing the reports. Fred Skaer recommended electronic
polling for the review by the Task Force.
Pat Haman asked whether the work
plans of the three Work Group could be made public before the Task Force
has approved the draft reports. The Task Force
agreed to this request, as well as the immediate posting of reference materials.
Mr.
Hoffman asked about why economic development as a purpose and need causes
any issues. Ms. Haman said that use of economic development in a project purpose
and need statement sometimes raises questions by resource agencies about
the
range of alternatives that should be considered, and whether these go beyond
the jurisdiction of the transportation agency. Moreover, some transportation
projects are not justified on the basis of a transportation need, and there
are question about whether a transportation project can deliver on its promises
of economic development. Chip Nottingham expressed concern that economic
development should not serve as a trump card to advance any transportation
project regardless
of its other effects, and noted that it is important to make sure the economic
development potential is real.
Indirect and Cumulative Impacts (ICI) Work
Group
Ted Boling said that the draft ICI report is ready for review by the
whole Task Force. The report characterizes the state of the practice and
identifies several overarching issues. First, the report notes the lack of
basic understanding
of indirect and cumulative impacts. There is clearly a need for improved
understanding of ICI among practitioners. Second, there is a need for clarification
on which
impacts need to be analyzed. There’s some good guidance out there (e.g.,
CEQ) but more could be helpful. Third, the report cites a need to address
the rigor of the analysis of ICI.
Mr. Boling said that the report addresses
several areas of disagreement, which
could be classified as either analytical or philosophical. Transportation
agencies are concerned about how much mitigation they are required to do for
actions
beyond their control. Others are concerned about the cumulative impacts of
development and see a need for mitigation to take place at some point. The
report includes a compendium of existing guidance materials and other resources
that the Work Group would like to see made available to the public.
Mr. Boling
said that the report identifies a series of opportunities for improvements
and has tiers of recommendations. First, to improve basic understanding of
ICI, the report recommends outreach and information sharing. Second, the
report recommends more advanced guidance for practitioners, to make what exists
more
specific and applicable to transportation projects. Third, the report calls
for new approaches to building consensus, including development of a coordination
model.
Integrated Planning Work Group
Carol Adkins said the Integrated Planning Work
Group’s draft report
is being billed as a deliberative draft. The Work Group feels a strong
need to get the report out to the public since planning is predominantly
a local
prerogative. The Work Group also has an aggressive outreach plan in mind.
The
Work Group started with developing a shared concept of integrated planning.
Under this concept, transportation is looked at as a system, across modes.
Transportation is also examined in the context of multiple systems and the
need to serve multiple goals, including transportation needs, economic development,
and environment quality. The Work Group then identified gaps in current practice
and identified some short-term as well as some longer-term solutions. Ms.
Adkins noted that all planning processes are not equal. The processes for transportation
planning and air-quality planning are prescribed by law, and these processes
are relatively standardized. Other planning processes are not standardized
to the same degree.
The Work Group found that agencies are not doing a good
job of accessing each other’s planning outputs. Agencies could also
do better at sharing data, such as through GIS systems. The Work Group found
a
need for more outreach
and for bringing more people to the table during planning.
The Work Group
report also cites need for federal policy leadership. Everyone is on board
with the idea of integrated planning but practitioners have questions
about their ability to do it under current laws and regulations. Guidance
in this area would be helpful.
The draft report cites a need for capacity-building
so that agencies understand each others’ planning processes better.
It also argues for institutional changes within agencies to reorient staff
and
resources toward integrated planning
efforts.
Ms. Adkins said that the Work Group would like to make its resource
materials available to the public immediately, and post the draft report
after 30 day
review by the Task Force. The Work Group is also looking for guidance from
the Task Force on whether the outreach plan goes too far or not far enough,
and if the timing of outreach activities for the report is of any concern
in regard to reauthorization.
VI. Presentation on the Montana US 93 Priority Project
Janice Weingart Brown, FHWA’s Montana Division Director gave a presentation
on the U.S. 93 priority project and the development of the Wildlife Habitat
Handbook. She said that the goal of the handbook is to allow mitigation banking
for wildlife habitat preservation.
Ms. Brown observed that the current project-by-project
review of ecological impacts is resulting in “postage-stamp mitigation” or
species-specific mitigation. She also said that the emphasis on on-site mitigation
is resulting
in lost opportunities for more effective mitigation.
Ms. Brown said that
there are vanishing opportunities for ecological preservation and that
an ecosystem approach can reduce administrative burdens, streamline
project delivery, and result in better ecological protection and mitigation.
She discussed the work on the US-93 project to create a credit and debit
bank for wildlife habitat preservation. She asked the Task Force Members
to support their agencies’ participants in the Steering Committee
and the US-93 Interagency Review Team.
Administrator Peters thanked Ms.
Brown for her presentation.
VII. Wrap-up
Administrator Peters asked Task Force Members to submit any comments
on the documents discussed during the meeting to Robert Mariner. She reminded
the Task Force Members that the Task Force would be using electronic polling
for approval on the public release of documents.
Ann Miller of EPA said
that her agency has found participation in the Task Force to be resource-intensive
and expressed EPA’s interest in having
the Task Force prioritize its efforts to get at the low-hanging fruit.
Administrator Peters agreed that such a discussion would be helpful.
Administrator
Peters adjourned the meeting at 3:42 pm. |