TAR PART 1231 - CONTRACT COST PRINCIPLES AND PROCEDURES
PART 1231 - CONTRACT COST PRINCIPLES AND PROCEDURES
SUBPART 1231.2--CONTRACTS WITH COMMERCIAL ORGANIZATIONS
1231.205 Selected costs.
1231.205-32 Precontract costs.
(a) The decision to incur precontract costs is that of the contractor. No DOT employee can authorize, demand, or require a contractor to incur precontract costs. The contracting officer may advise the prospective contractor that any costs incurred before contract award are at the contractor's sole risk and that if negotiations fail to result in a binding contract, payment of these costs may not be made by the Government.
(b) When the contracting officer determines that incurring precontract costs was necessary to meet the proposed contract delivery schedule of a cost-reimbursement contract, the clause at (TAR) 48 CFR 1252.231-70, Date of Incurrence of Costs, may be inserted in the resultant contract.
TAR SECTIONS
- TAR Main Page
- Part 1201
- Part 1202
- Part 1203
- Part 1204
- Part 1205
- Part 1206
- Part 1207
- Part 1211
- Part 1213
- Part 1214
- Part 1215
- Part 1216
- Part 1217
- Part 1219
- Part 1222
- Part 1223
- Part 1224
- Part 1227
- Part 1228
- Part 1231
- Part 1232
- Part 1233
- Part 1235
- Part 1236
- Part 1237
- Part 1239
- Part 1242
- Part 1245
- Part 1246
- Part 1247
- Part 1252
- Part 1253